The Last Planner Boards in construction are an essential element in your Lean journey and using a scoreboard is a great way to visualize multiple metrics of the Last Planner System as well as to help keep the team motivated. Lean expert and co-author of The Lean Builder: A Builder’s Guide to Applying Lean Tools in the Field, Keyan Zandy demonstrates how to utilize visual communication boards as a method of Last Planner System scorekeeping on the jobsite.
Are You Keeping Score?
Scorekeeping Through Last Planner Boards
Have you heard the phrase, “If it’s worth doing, it’s worth measuring”?
How about, “You can’t get to where you’re going if you don’t know where you’re at”?
Both sayings come at the same concept from different angles: the importance of keeping track of your progress. And keeping track can easily translate to keeping score.
Starting several years back, when I would visit jobsites, I started asking trade partners if they knew what milestone or completion dates they were working towards. I was surprised to find that they often didn’t—sometimes, they didn’t even know fore sure what date the project was supposed to be complete!
“We are pushing hard,” I would hear. “We’ll get there.”
I asked one of my superintendents if he was issuing a six-week look-ahead every week. He affirmed that he was, showing me a multi-page Gantt schedule that he said went out each Friday. But as much as we talk about scheduling and spend effort pull planning and creating weekly work plans, the fact is most foremen (and especially their craftspeople) do not know milestones or completion dates. They are just working as hard as they can.
I shared this frustration with a mentor of mine, and he suggested I read the book The 4 Disciplines of Execution by Chris McChesney. I burned through it and was fascinated with the third discipline, which discusses the importance of keeping a compelling scoreboard.
According to the authors, people and teams play differently when the score is being kept, and the right kind of scoreboards motivate players to win. This concept was a gamechanger for me. I kept asking myself: how can we keep score in our industry? How can we be more transparent with the field? How can we create a scoreboard that compels action, and keeps energy and intensity directed towards the key milestones of the project?
The Last Planner System™ in Construction
Luckily for us, the Last Planner System covers many of these metrics—but it’s up to us to make them visual. So, how can we achieve this?
#1 – Keep it simple.
Our main scoreboard has only four metrics on it:
- Days ahead/behind the current milestone,
- Days ahead/behind on the overall schedule,
- Weather days, and
- Days remaining in the project.
(Yes, we share the real number of days remaining in the project with our trade partners. We are a team, and we should all be dialed in to the amount of time left in the project. Every day counts, and we should all know what’s left on the timeclock.)
#2 – Make it easy to tell if you’re winning or losing.
Use colors, charts, infographics, etc., to make sure the field can easily understand the score and the metrics being tracked. The Last Planner System’s™ Three-Week Look-Ahead and Percent Plan Complete tools are great places to start. Our three-week look-ahead boards display upcoming milestones dates for the field teams to reference.
#3 – Percent Plan Complete Boards
Our Percent Plan Complete boards track the score of how well the team is keeping their commitments to one another. The Percent Plan Complete board can be printed on plotter paper or drawn onto a whiteboard; either way, it should be displayed where you will be having your daily huddles. You can build your Percent Plan Complete board with the following categories:
- Activities Completed
- Activities Promised
- Weekly Team Percentage
- Root Cause Categories
- Root Causes for Work Missed
- Twelve-Week Snapshot
After your final huddle of the week, tally up the number of activities completed and divide by the number of the activities promised. This will yield a percentage of commitments met.
You can also track root causes for work that was not completed. Predetermined root causes for missed commitments are:
- Weather,
- Manpower,
- Machinery,
- Design,
- Make-ready,
- Materials,
- Poor scheduling, and
- Other
A root cause pie chart can be a great way visually understand what categories the root causes are coming from. And by dividing the number of root cause types by the number of missed commitments, you will have the root cause percentage by type. This helps to identify trends on the project, such as manpower shortages, slow design response times, and weather impacts.
#4 – Make it public.
It’s important that your scoreboards are in a place where the trade partners can see them. Upcoming milestones, days left in the project, commitments made/missed are all displayed as part of our Lean dashboard system, which is accessible to everyone. Sharing goals, progress, success, and failures with the team increases the odds that accountability will set in and performance will improve. Post this information up around the jobsite. Turn up the heat and see the results that you achieve.
#5 – Update it every week.
Update your visual metrics weekly. Your teams need accurate information, and it will allow foremen to have conversations with their tradespeople about weekly results, improved performance, and constraints that may be in the way of an upcoming milestone. By closely watching the handful of scores that really matter, the field can be more flexible and change strategy if needed.
Great field teams know—every day—if they are currently successful and what is required to win the game. It’s important that we share metrics that explain where the field is versus where they should be, because this information allows field leaders to solve real problems and make informed decisions.